The scope of work shall consist of but not limited to the following: The City of Chattanooga is seeking a general contractor to build, hire and manage trades, and provide oversight and management for the redevelopment and construction of a new city park at 1785 Reggie White Boulevard encompassing the site of the existing Chattanooga Skate Park. The existing Chattanooga Skate Park will be almost entirely demolished and replaced with a new formed in place, in ground, concrete skate park to be constructed by others under the supervision of the General Contractor. The general contractor will be directly responsible for performing and coordinating all work and tradespeople for the remainder of the park construction. These responsibilities include but are not necessarily limited to: demolitions, grading, drainage, hardscape, landscape, irrigation, lighting, electrical, plumbing, construction of a bathroom / maintenance building, fencing, ADA facilities, parking lot striping, and site furnishings. The project site is governed by a soil management plan which must be followed at all times. The project site contains an existing roller rink which will remain in place. Parking, access, and construction staging will require coordination with adjacent property owners under the terms of a existing parking management and lease agreements.
Background
The City of Chattanooga is undertaking a project to redevelop and construct a new city park at 1785 Reggie White Boulevard, which will include the construction of a new skate park. The existing Chattanooga Skate Park will be demolished and replaced with a new in-ground concrete skate park.
The general contractor will be responsible for overseeing all aspects of the construction, including managing trades and ensuring compliance with a soil management plan.
Work Details
The scope of work includes: demolitions, grading, drainage, hardscape, landscape, irrigation, lighting, electrical work, plumbing, construction of a bathroom/maintenance building, fencing, ADA facilities, parking lot striping, and site furnishings.
Specific tasks include:
- Demolition of existing structures including curb (430 LF), sidewalk (920 SF), concrete from the existing skate park (28,540 SF), trees (4), and fence (1,530 LF).
- Installation of underground utilities such as new underground electric (25 LF), water lateral (25 LF), sewer lateral (25 LF), and storm pipes of various sizes.
- Grading and earthwork including on-site cut and fill operations.
- Erosion control measures including silt fences and temporary sediment traps.
- Hardscape installation including concrete walkways (22,100 SF) and heavy-duty concrete areas (1,600 SF).
- Softscape installation including new trees (69) and sod areas (40,100 SF).
- Construction of site amenities such as benches (11), trash receptacles (15), bike racks (5), shade structures (4), and bollards (15).
Period of Performance
The contract period is expected to commence upon award and continue through the completion of all construction activities as outlined in the project schedule.
Place of Performance
The contract work will be performed at 1785 Reggie White Boulevard in Chattanooga, Tennessee.