CONSTRUCTION OF MUD MOUNTAIN DAM FISH PASSAGE FACILITY IN BUCKLEY, WA
Awardee
Awarding Agency
Funding Agency
Place of Performance
Enumclaw, WA 98022 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Related Opportunity
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 09/20/22 to 12/31/25 and the Potential Award value has increased 15% from $132,349,204 to $152,101,531.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Kiewit Infrastructure West was awarded
Definitive Contract W912DW18C0011 (W912DW-18-C-0011)
for Construction Of Mud Mountain Dam Fish Passage Facility In Buckley, Wa
worth up to $152,101,531
by the U.S. Army Corps of Engineers
in March 2018.
The contract
has a duration of 7 years 9 months and
was awarded
through solicitation Mud Mountain Dam Fish Passage Facility, Buckley, WA
full & open
with
NAICS 237990 and
PSC Y1PZ
via direct negotiation acquisition procedures with 5 bids received.
As of today, the Definitive Contract has a total reported backlog of $75,000.
DOD Announcements
Mar 2018:
Kiewit Infrastructure West Co., Vancouver, Washington, has been awarded an $112,047,000 firm-fixed-price contract for construction of a fish passage facility at Mud Mountain Dam in Buckley, Washington. Bids were solicited via the Internet with five received. Work will be performed in Buckley, Washington, with an estimated completion date of Sept. 20, 2022. Fiscal 2018 general construction funds in the amount of $6,757,000 were obligated at the time of the award. U.S. Army Corps of Engineers, Seattle, Washington, is the contracting activity (W912DW-18-C-0011).
Feb 2020: Kiewit Infrastructure West Co, Vancouver, Washington, was awarded a $10,150,000 modification (P00017) to contract W912DW-18-C-0011 for construction of a fish passage facility at Mud Mountain Dam. Work will be performed in Buckley, Washington, with an estimated completion date of Sept. 22, 2022. Fiscal 2018 civil construction funds in the amount of $10,150,000 were obligated at the time of the award. U.S. Army Corps of Engineers, Seattle, Washington, is the contracting activity.
May 2024: Kiewit Infrastructure West Co., Vancouver, Washington, was awarded a $7,562,585 modification (P00027) to contract W912DW-18-C-0011 for the Mud Mountain Dam Fish Passage Facility. Work will be performed in Enumclaw, Washington, with an estimated completion date of Dec. 31, 2025. Fiscal 2024 civil operation and maintenance funds in the amount of $7,319,448 were obligated at the time of the award. U.S. Army Corps of Engineers, Seattle, Washington, is the contracting activity.
Feb 2020: Kiewit Infrastructure West Co, Vancouver, Washington, was awarded a $10,150,000 modification (P00017) to contract W912DW-18-C-0011 for construction of a fish passage facility at Mud Mountain Dam. Work will be performed in Buckley, Washington, with an estimated completion date of Sept. 22, 2022. Fiscal 2018 civil construction funds in the amount of $10,150,000 were obligated at the time of the award. U.S. Army Corps of Engineers, Seattle, Washington, is the contracting activity.
May 2024: Kiewit Infrastructure West Co., Vancouver, Washington, was awarded a $7,562,585 modification (P00027) to contract W912DW-18-C-0011 for the Mud Mountain Dam Fish Passage Facility. Work will be performed in Enumclaw, Washington, with an estimated completion date of Dec. 31, 2025. Fiscal 2024 civil operation and maintenance funds in the amount of $7,319,448 were obligated at the time of the award. U.S. Army Corps of Engineers, Seattle, Washington, is the contracting activity.
Status
(Open)
Last Modified 1/21/25
Period of Performance
3/14/18
Start Date
12/31/25
Current End Date
12/31/25
Potential End Date
Obligations and Backlog
$152.0M
Total Obligated
$152.0M
Current Award
$152.1M
Potential Award
$0.0
Funded Backlog
$75.0K
Total Backlog
Award Hierarchy
Definitive Contract
W912DW18C0011
Subcontracts
Activity Timeline
Subcontract Awards
Disclosed subcontracts for W912DW18C0011
Opportunity Lifecycle
Procurement history for W912DW18C0011
Transaction History
Modifications to W912DW18C0011
People
Suggested agency contacts for W912DW18C0011
Competition
Number of Bidders
5
Solicitation Procedures
Negotiated Proposal/Quote
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
Construction
IT Commercial Item Category
Not Applicable
Awardee UEI
YSNNL4FGAQ53
Awardee CAGE
4TJJ4
Agency Detail
Awarding Office
W912DW W071 ENDIST SEATTLE
Funding Office
960102
Created By
thomas.j.parsons@usace.army.mil
Last Modified By
thomas.j.parsons@usace.army.mil
Approved By
thomas.j.parsons@usace.army.mil
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Performance District
WA-08
Senators
Maria Cantwell
Patty Murray
Patty Murray
Representative
Kim Schrier
Budget Funding
Federal Account | Budget Subfunction | Object Class | Total | Percentage |
---|---|---|---|---|
Construction, Corps of Engineers - Civil (096-3122) | Water resources | Land and structures (32.0) | $37,044,572 | 100% |
Modified: 1/21/25