W9127N22C0009

Definitive Contract

Overview

Government Description
WEST COAST HOPPER MAINTENANCE DREDGING 2022
Alternate Description
est Coast Hopper Maintenance Dredging 2022
Place of Performance
Portland, OR 97204 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Analysis Notes
Forecast Listed as the incumbent award in contract forecast West Coast Hopper Dredging 2023.
Amendment Since initial award the Potential End Date has been shortened from 03/15/23 to 12/15/22.
Predecessor This appears to be a continuation of a prior contract W9127N21C0019.
Successor The following contract appears to have succeeded this one W9127N23C0005.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Unrealized Backlog This Definitive Contract is complete with $4,725,000 of unfunded backlog unused.
Manson Construction Co was awarded Definitive Contract W9127N22C0009 (W9127N-22-C-0009) for West Coast Hopper Maintenance Dredging 2022 worth up to $27,996,801 by the U.S. Army Corps of Engineers in March 2022. The contract has a duration of 9 months and was awarded through solicitation West Coast Hopper Dredge FY22 full & open with NAICS 237990 and PSC Y1KF via sealed bid acquisition procedures with 1 bid received. As of today, the Definitive Contract has a total reported backlog of $4,725,000, though the contract is complete, so backlog may not be realized.

DOD Announcements

Mar 2022: Manson Construction Co., Seattle, Washington, was awarded a $19,628,500 firm-fixed-price contract for dredging the Humboldt Bay Bar, the mouth of the Columbia River and the Lower Columbia River. Bids were solicited via the internet with one received. Work will be performed in Portland, Oregon, with an estimated completion date of March 15, 2023. Fiscal 2022 civil operation and maintenance funds in the amount of $19,628,500 were obligated at the time of the award. U.S. Army Corps of Engineers, Portland, Oregon, is the contracting activity (W9127N-22-C-0009).

Status
(Complete)

Last Modified 1/17/23
Period of Performance
3/23/22
Start Date
12/15/22
Current End Date
12/15/22
Potential End Date
100% Complete

Obligations and Backlog
$23.3M
Total Obligated
$23.3M
Current Award
$28.0M
Potential Award
83% Funded
$0.0
Funded Backlog
$4.7M
Total Backlog

Award Hierarchy

Definitive Contract

W9127N22C0009

Subcontracts

-

Activity Timeline

Interactive chart of timeline of amendments to W9127N22C0009

Subcontract Awards

Disclosed subcontracts for W9127N22C0009

Opportunity Lifecycle

Procurement history for W9127N22C0009

Transaction History

Modifications to W9127N22C0009

People

Suggested agency contacts for W9127N22C0009

Competition

Number of Bidders
1
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
Construction
IT Commercial Item Category
Not Applicable
Awardee UEI
UJGKNVYG6UZ3
Awardee CAGE
0FCP9
Agency Detail
Awarding Office
W9127N US ARMY ENGINEER DISTRICT PORTLAND
Funding Office
None
Created By
mitchell.j.johnson@usace.army.mil
Last Modified By
mitchell.j.johnson@usace.army.mil
Approved By
mitchell.j.johnson@usace.army.mil

Legislative

Legislative Mandates
Construction Wage Rate Requirements
Performance District
OR-03
Senators
Jeff Merkley
Ron Wyden
Representative
Earl Blumenauer

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Operation and Maintenance, Corps of Engineers-Civil (096-3123) Water resources Land and structures (32.0) $22,967,938 100%