W9126G22C0013
Definitive Contract
Overview
Government Description
HAMMERHEAD BARRACKS BUILDING 10020 - 10022
Awardee
Awarding / Funding Agency
Place of Performance
Fort Hood, TX 76544 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Related Opportunity
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 10/01/24 to 11/09/24 and the Potential Award value has increased 1% from $59,140,000 to $59,761,588.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Guyco was awarded
Definitive Contract W9126G22C0013 (W9126G-22-C-0013)
for Hammerhead Barracks Building 10020 - 10022
worth up to $59,761,588
by USACE Fort Worth District
in August 2022.
The contract
has a duration of 2 years 3 months and
was awarded
through solicitation FY22 Phase 2 Repair Hammerhead Barracks Building 10020, 10021 and 10022, Fort Hood, Texas
full & open
with
NAICS 236220 and
PSC Y1FC
via two step acquisition procedures with 2 bids received.
DOD Announcements
Aug 2022:
Guyco Inc., Lampasas, Texas, was awarded a $59,140,000 firm-fixed-price contract for renovation of hammerhead barracks. Bids were solicited via the internet with two received. Work will be performed at Fort Hood, Texas, with an estimated completion date of Oct. 1, 2024. Fiscal 2022 operation and maintenance, Army funds in the amount of $59,140,000 were obligated at the time of the award. U.S. Army Corps of Engineers, Fort Worth, Texas, is the contracting activity (W9126G-22-C-0013).
Status
(Complete)
Last Modified 5/24/24
Period of Performance
8/11/22
Start Date
11/9/24
Current End Date
11/9/24
Potential End Date
Obligations
$59.8M
Total Obligated
$59.8M
Current Award
$59.8M
Potential Award
Award Hierarchy
Definitive Contract
W9126G22C0013
Subcontracts
Activity Timeline
Opportunity Lifecycle
Procurement history for W9126G22C0013
Transaction History
Modifications to W9126G22C0013
People
Suggested agency contacts for W9126G22C0013
Competition
Number of Bidders
2
Solicitation Procedures
Two Step
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
Construction
IT Commercial Item Category
Not Applicable
Awardee UEI
M5L5TNSE6A15
Awardee CAGE
0CZ08
Agency Detail
Awarding Office
W9126G W076 ENDIST FT WORTH
Funding Office
W9126G
Created By
andrew.r.bury@usace.army.mil
Last Modified By
andrew.r.bury@usace.army.mil
Approved By
andrew.r.bury@usace.army.mil
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Performance District
TX-31
Senators
John Cornyn
Ted Cruz
Ted Cruz
Representative
John Carter
Budget Funding
Federal Account | Budget Subfunction | Object Class | Total | Percentage |
---|---|---|---|---|
Operation and Maintenance, Army (021-2020) | Department of Defense-Military | Land and structures (32.0) | $57,703,744 | 100% |
Modified: 5/24/24