W9126G19C0118

Definitive Contract

Overview

Government Description
DESIGN BUILD CONSTRUCTION CONTRACT FOR RIO GRANDE VALLEY (RGV04) FENCE SEGMENT, HIDALGO COUNTY, TX.
Alternate Description
Rio Grande Valley (RGV) 04 Fence Segment
Place of Performance
Mcallen, TX 78501 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Related Opportunity
W9126G19R0118
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 05/25/21 to 07/28/23 and the Potential Award value has increased 7% from $304,600,000 to $326,937,677.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Unrealized Backlog This Definitive Contract is complete with $47,999 of funded backlog and $47,999 of unfunded backlog unused, which is typically due to unexercised options.
Southwest Valley Constructors Co was awarded Definitive Contract W9126G19C0118 (W9126G-19-C-0118) for Design Build Construction Contract For Rio Grande Valley (RGV04) Fence Segment, Hidalgo County, Tx. worth up to $326,937,677 by USACE Fort Worth District in August 2019. The contract has a duration of 4 years and was awarded full & open with NAICS 237310 and PSC Y1LB via direct negotiation acquisition procedures with 3 bids received. As of today, the Definitive Contract has a total reported backlog of $47,999 and funded backlog of $47,999, though the contract is complete, so backlog may not be realized.

DOD Announcements

Aug 2019: Southwest Valley Constructors Co., Albuquerque, New Mexico, was awarded an $80,869,000 contract for design-build horizontal construction in support of the Department of Homeland Security in McAllen, Texas.  Three bids were solicited with three bids received.  Work will be performed in McAllen, Texas, with an estimated completion date of April 28, 2021.  Fiscal 2019 Department of Homeland Security funds in the amount of $80,869,000 were obligated at the time of the award.  U.S. Army Corps of Engineers, Fort Worth, Texas, is the contracting activity (W9126G-19-C-0118).

Status
(Complete)

Last Modified 11/28/23
Period of Performance
8/7/19
Start Date
7/28/23
Current End Date
7/28/23
Potential End Date
100% Complete

Obligations and Backlog
$326.9M
Total Obligated
$326.9M
Current Award
$326.9M
Potential Award
100% Funded
$48.0K
Funded Backlog
$48.0K
Total Backlog

Award Hierarchy

Definitive Contract

W9126G19C0118

Subcontracts

-

Activity Timeline

Interactive chart of timeline of amendments to W9126G19C0118

Subcontract Awards

Disclosed subcontracts for W9126G19C0118

Transaction History

Modifications to W9126G19C0118

People

Suggested agency contacts for W9126G19C0118

Competition

Number of Bidders
3
Solicitation Procedures
Negotiated Proposal/Quote
Evaluated Preference
None
Performance Based Acquisition
Yes
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
Construction
IT Commercial Item Category
Not Applicable
Awardee UEI
W31DQKBPJCD3
Awardee CAGE
7V2D3
Agency Detail
Awarding Office
W9126G W076 ENDIST FT WORTH
Funding Office
W9126G
Created By
robin.g.prince2@usace.army.mil
Last Modified By
robin.g.prince2@usace.army.mil
Approved By
robin.g.prince2@usace.army.mil

Legislative

Legislative Mandates
Construction Wage Rate Requirements Labor Standards Materials, Supplies, Articles & Equipment
Performance District
TX-15
Senators
John Cornyn
Ted Cruz
Representative
Mónica De La Cruz
Modified: 11/28/23