Government Description
DESIGN BUILD CONSTRUCTION SERVICES TO RENOVATE AND UPGRADE THE HILL AIR FORCE BASE BUILDING 1286 STEAM PLANT.
Awardee
Awarding / Funding Agency
Place of Performance
Highland, UT 84003 United States
Pricing
Fixed Price
Set Aside
Small Business Set Aside - Total (SBA)
Extent Competed
Full And Open Competition After Exclusion Of Sources
Related Opportunity
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 03/20/24 to 04/15/25 and the Potential Award value has increased from $21,736,639 to $21,818,304.
Unrealized Backlog This Definitive Contract is complete with $66,292 of funded backlog and $66,292 of unfunded backlog unused, which is typically due to unexercised options.
Unrealized Backlog This Definitive Contract is complete with $66,292 of funded backlog and $66,292 of unfunded backlog unused, which is typically due to unexercised options.
NH1 JV was awarded
Definitive Contract W9123822C0023 (W91238-22-C-0023)
for Design Build Construction Services To Renovate And Upgrade The Hill Air Force Base Building 1286 Steam Plant.
worth up to $21,818,304
by USACE Sacramento District
in September 2022.
The contract
has a duration of 2 years 7 months and
was awarded
through solicitation USACE SPK DB Construction - Building 1286 Steam Plant Upgrades at Hill AFB, UT
with a Small Business Total set aside
with
NAICS 236220 and
PSC Z2NB
via two step acquisition procedures with 3 bids received.
As of today, the Definitive Contract has a total reported backlog of $66,292 and funded backlog of $66,292, though the contract is complete, so backlog may not be realized.
DOD Announcements
Sep 2022:
NH1 JV,* Highland, Utah, was awarded a $21,736,639 firm-fixed-price contract to replace existing boilers with new dual-fuel boilers. Bids were solicited via the internet with three received. Work will be performed in Hill Air Force Base, Utah, with an estimated completion date of March 24, 2025. Fiscal 2022 operation and maintenance, Air Force funds in the amount of $21,736,639 were obligated at the time of the award. U.S. Army Corps of Engineers, Sacramento, California, is the contracting activity (W91238-22-C-0023).
Status
(Complete)
Last Modified 9/19/24
Period of Performance
9/22/22
Start Date
4/15/25
Current End Date
4/15/25
Potential End Date
Obligations and Backlog
$21.8M
Total Obligated
$21.8M
Current Award
$21.8M
Potential Award
$66.3K
Funded Backlog
$66.3K
Total Backlog
Award Hierarchy
Definitive Contract
W9123822C0023
Subcontracts
Activity Timeline
Opportunity Lifecycle
Procurement history for W9123822C0023
Transaction History
Modifications to W9123822C0023
People
Suggested agency contacts for W9123822C0023
Competition
Number of Bidders
3
Solicitation Procedures
Two Step
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Plan Not Required
Cost Accounting Standards
Exempt
Business Size Determination
Small Business
Defense Program
None
DoD Claimant Code
Construction
IT Commercial Item Category
Not Applicable
Awardee UEI
NS7TRNRTKWG4
Awardee CAGE
948U3
Agency Detail
Awarding Office
W91238 W075 ENDIST SACRAMENTO
Funding Office
W91238
Created By
christopher.s.paxman@usace.army.mil
Last Modified By
christopher.s.paxman@usace.army.mil
Approved By
christopher.s.paxman@usace.army.mil
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Performance District
UT-03
Senators
Mike Lee
Mitt Romney
Mitt Romney
Representative
John Curtis
Budget Funding
Federal Account | Budget Subfunction | Object Class | Total | Percentage |
---|---|---|---|---|
Military Construction, Army (021-2050) | Department of Defense-Military | Land and structures (32.0) | $21,736,639 | 100% |