Search Prime Contracts

W911XK20C0018

Definitive Contract

Overview

Government Description
CONSTRUCTION OF UPSTREAM APPROACH WALLS, NEW SOO LOCK COMPLEX, SAULT STE. MARIE, MI.
Place of Performance
Sault Sainte Marie, MI 49783 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 10/15/23 to 09/17/24 and the Potential Award value has increased 12% from $145,456,000 to $163,618,800.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Unrealized Backlog This Definitive Contract is complete with $28,545,000 of unfunded backlog unused.
Kokosing Alberici was awarded Definitive Contract W911XK20C0018 (W911XK-20-C-0018) for Construction Of Upstream Approach Walls, New Soo Lock Complex, Sault Ste. Marie, Mi. worth up to $163,618,800 by the U.S. Army Corps of Engineers in August 2020. The contract has a duration of 4 years 1 months and was awarded through solicitation Upstream Approach Wall Construction for the Soo Lock Complex, Sault Ste. Marie, MI. full & open with NAICS 237990 and PSC Y1KA via direct negotiation acquisition procedures with 3 bids received. As of today, the Definitive Contract has a total reported backlog of $28,545,000, though the contract is complete, so backlog may not be realized.

DOD Announcements

Sep 2020: Kokosing Alberici LLC, Westerville, Ohio, was awarded an $111,259,000 firm-fixed-price contract for construction of new upstream approach walls at the Soo Lock Complex, Sault Ste. Marie, Michigan.  Bids were solicited via the internet with three received.  Work will be performed in Sault Ste. Marie, Michigan, with an estimated completion date of Oct. 16, 2023.  Fiscal 2020 civil construction funds in the amount of $111,259,000 were obligated at the time of the award.  U.S. Army Corps of Engineers, Detroit, Michigan, is the contracting activity (W911XK-20-C-0018).

Status
(Complete)

Last Modified 9/6/24
Period of Performance
8/31/20
Start Date
9/17/24
Current End Date
9/17/24
Potential End Date
100% Complete

Obligations and Backlog
$135.1M
Total Obligated
$135.1M
Current Award
$163.6M
Potential Award
83% Funded
$0.0
Funded Backlog
$28.5M
Total Backlog

Award Hierarchy

Definitive Contract

W911XK20C0018

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to W911XK20C0018

Opportunity Lifecycle

Procurement history for W911XK20C0018

Transaction History

Modifications to W911XK20C0018

People

Suggested agency contacts for W911XK20C0018

Competition

Number of Bidders
3
Solicitation Procedures
Negotiated Proposal/Quote
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Yes
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
Construction
IT Commercial Item Category
Not Applicable
Awardee UEI
YFTZQV1NPKJ9
Awardee CAGE
8LA97
Agency Detail
Awarding Office
W911XK W072 ENDIST DETROIT
Funding Office
965401
Created By
glenn.w.moon@usace.army.mil
Last Modified By
glenn.w.moon@usace.army.mil
Approved By
glenn.w.moon@usace.army.mil

Legislative

Legislative Mandates
Construction Wage Rate Requirements
Performance District
MI-01
Senators
Debbie Stabenow
Gary Peters
Representative
Jack Bergman

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Construction, Corps of Engineers - Civil (096-3122) Water resources Land and structures (32.0) $111,546,118 100%
Modified: 9/6/24