Pineview Reservoir Recreation Complex Reconstruction – Port Boat Ramp Ogden Ranger District, Uinta Wasatch, Cache National Forest, Weber, Utah

ID: 1131540 • Type: Special Notice

Description

Posted: Oct. 8, 2024, 10:32 a.m. EDT

NOTE: THE PRE-SOLICITATION FALL SITE VISIT NOTIFICATION HAS BEEN UPDATED TO ADD THE FOLLOWING ATTACHMENTS: STATEMENT OF WORK, SPECIFICIATIONS AND DRAWINGS.

PRE-SOLICITATION FALL SITE VISIT ONLY, THIS IS NOT A SOLICITATION

Project Title: Pineview Reservoir Recreation Complex Reconstruction Port Boat Ramp, Ogden Ranger District, Uinta Wasatch, Cache National Forest, Weber, Utah

Project Summary:

This project includes all labor, materials and equipment to reconstruct the existing Port Ramp Day Use Area at Pineview Reservoir near Huntsville, UT. The site is owned by the Ogden Ranger District of the Uinta Wasatch, Cache National Forest.

Work Includes:

1. Removal and disposal of existing structures and site furnishings.

2. Removal and salvage to USFS of existing precast concrete vault comfort stations.

3. Preservation of existing accesses onto Snow Basin property.

4. Obliterating, scarifying, and regrading existing roadways and paths.

5. Construction of SR-158 road improvements, entry road, entry booths, and exit road.

6. Construction of storm drainage improvements: culverts, flared end sections, trash

racks, catch basins, treatment devices, and drainage channels.

7. Construction of rock rip rap slope protection.

8. Construction of entry gates.

9. Construction of concrete stairs.

10. Construction of precast concrete vault comfort stations.

11. Construction of new dump station.

12. Construction of improvements around Utah Division of Water Resources (DWR) decontamination area.

13. Construction of a new parking lot area.

14. Construction of new booster pump station with associated water connections to dump station, future concessionaire building, and host sites.

15. Construction of host sites with utility hookups.

16. Construction of sanitary sewer system for dump station and host sites with underground wastewater storage tanks.

17. Construction of trash enclosures.

18. Construction of pavilions (i.e. shade structures) with picnic and utility tables.

Site Visit Information:

Date: Friday November 15, 2024.

Time: 10:00 AM MST

Where: Pineview Trail Head

Access: Approx. 6.5 miles East of the mouth of Ogden Canyon along Hwy 158 41 15'56.25"N 111 49'28.52"W, Ogden, Utah.

POC/Telephone Number: Oscar Mena 801-554-9916

A Forest Service site visit of the units will be at the Pineview Trail Head at 10:00 AM MST on Friday November 15, 2024. Those participating in the site visit must furnish their own transportation and may wish to bring a lunch. Please inform the District Office if you plan to attend by calling POC at 801-554-9916 by noon of the day before the site visit.

The function of the Forest Service site visit is to show the on-the-ground location of the work areas, boundaries and other in-place markers, and the routes of travel that may be utilized in going to and from the work areas.

Directions and Access:

Approx. 6.5 miles East of the mouth of Ogden Canyon along Hwy 158 41 15'56.25"N 111 49'28.52"W, Ogden, Utah. Some areas are located behind locked gates and must be viewed on the scheduled site visit, or "walk-in" may be required. Interested parties desiring to visit units on their own should coordinate travel with Oscar Mena COR at 801-554-9916.

MAGNITUDE OF CONSTRUCTION PROJECT

More than $10,000,000.00

Posted: Oct. 2, 2024, 9:38 a.m. EDT
Background
The project is initiated by the USDA Forest Service, specifically the Ogden Ranger District of the Uinta Wasatch, Cache National Forest.

The mission of this contract is to reconstruct the Pineview Reservoir Recreation Complex, focusing on enhancing recreational facilities and improving access for visitors. The goal is to provide a safe and enjoyable environment for day-use activities at the Port Boat Ramp area.

Work Details
The scope of work includes:
1. Removal and disposal of existing structures and site furnishings.
2. Removal and salvage of existing precast concrete vault comfort stations to the USFS.
3. Preservation of existing accesses onto Snow Basin property.
4. Obliterating, scarifying, and regrading existing roadways and paths.
5. Construction of SR-158 road improvements, entry road, entry booths, and exit road.
6. Construction of storm drainage improvements including culverts, flared end sections, trash racks, catch basins, treatment devices, and drainage channels.
7. Construction of rock rip rap slope protection.
8. Construction of entry gates.
9. Construction of concrete stairs.
10. Construction of new precast concrete vault comfort stations.
11. Construction of a new dump station with associated water connections to future concessionaire building and host sites.
12. Construction of improvements around Utah Division of Water Resources (DWR) decontamination area.
13. Construction of a new parking lot area including trailer parking and rockery walls.
14. Construction of sidewalks, trails, beach access, trash enclosures, pavilions (shade structures) with picnic tables.

Period of Performance
The contract is expected to commence in May 2024 and will have a base bid duration of 180 calendar days.

Place of Performance
The construction projects will be performed at Pineview Reservoir near Huntsville, Utah, specifically within the Ogden Ranger District.

Overview

Response Deadline
Nov. 14, 2024, 2:00 p.m. EST Past Due
Posted
Oct. 2, 2024, 9:38 a.m. EDT (updated: Oct. 8, 2024, 10:32 a.m. EDT)
Set Aside
None
Place of Performance
South Jordan, UT 84095 United States
Source
SAM

Current SBA Size Standard
$45 Million
Pricing
Likely Fixed Price
Est. Value Range
Experimental
$500,000 - $1,500,000 (AI estimate)
Signs of Shaping
95% of similar contracts within the Forest Service had a set-aside.
On 10/2/24 Forest Service issued Special Notice 1131540 for Pineview Reservoir Recreation Complex Reconstruction – Port Boat Ramp Ogden Ranger District, Uinta Wasatch, Cache National Forest, Weber, Utah due 11/14/24.
Primary Contact
Name
Holly Hlavac   Profile
Phone
None

Secondary Contact

Name
Lucas Dahlman   Profile
Phone
None

Documents

Posted documents for Special Notice 1131540

Question & Answer

Incumbent or Similar Awards

Contracts Similar to Special Notice 1131540

Potential Bidders and Partners

Awardees that have won contracts similar to Special Notice 1131540

Similar Active Opportunities

Open contract opportunities similar to Special Notice 1131540

Additional Details

Source Agency Hierarchy
AGRICULTURE, DEPARTMENT OF > FOREST SERVICE
FPDS Organization Code
12C2-12C2
Source Organization Code
100013241
Last Updated
Nov. 30, 2024
Last Updated By
holly.hlavac@usda.gov
Archive Date
Nov. 29, 2024