Posted: Sept. 11, 2024, 5:36 p.m. EDT

The DARC program is part of a larger effort of moving towards a resilient space enterprise in our nation's Space Domain Awareness (SDA) capabilities able to deter aggression. The DARC Program of Record effort will build and install a pseudo-monostatic ground-based radar system. It will coherently combine the pseudo-monostatic array of steerable parabolic antennas. DARC provides a unique capability that is critical to ensure the Space Force and DoD are able to successfully execute the SDA mission. More detailed information on the SDA mission analysis, threat, and operational acceptance need dates identified below is classified. The complete DARC system will consist of 3 geographically dispersed sites approximately 120 degrees apart for world-wide GEO belt coverage. The Under Secretary of Defense for Acquisition and Sustainment (USD(A&S)) approved DARC Site 1 to proceed as a Middle Tier Acquisition (MTA) Rapid Prototype. DARC Sites 2 and 3 are planned to be acquired via the Major Capability Acquisition (MCA) pathway.

This acquisition will consist of the complete fielding of Sites 2 and 3; contractor logistics support for operations and support for all 3 Sites and Mission Operations Center (MOC) (Site 1 CLS limited to 2 years following Site 1 operational acceptance; Sites 2 and 3 CLS limited to 1 year each following each site operational acceptance); and the training of site operations and maintenance personnel for all 3 Sites and the MOC. The estimated contract award date for this Fielding action is Dec 2023 or 1 Qtr CY24 at the latest. The required Site 2 Operational Acceptance (OA) date is June 2028 and Site 3 QA is June 2029.

The two critical path items to meet the Site 2 operational capability date are production of the hardware subsystems and site construction. For example, the twenty-seven 15-meter dish antennas are currently the longest lead-time subsystem. Long- lead material for the antennas must be ordered NLT 2 Qtr 2024 (CY) such that all 27 antennas can be produced, delivered to site, and installed NLT 3 Qtr 2026 (CY) so that integration and test activities can begin NLT 1 Qtr 2027 (CY) to meet the operational capability date. The Architecture and Engineering (A&E) design, long- lead construction material orders, and approval processes must begin NLT 2 Qtr 2024 (CY) so that integration and test activities can begin 1 Qtr 2027 (CY).

The Government obtained Government Purpose Rights to Intellectual Property for Site 1 and expects the same for Sites 2 and 3. The Government will obtain the minimum rights sufficient to operate, train, maintain and install new equipment and 3rd party software in an Open Systems Architecture environment. If contractor asserts other than Government Purpose Rights, the RFP will include Firm Fixed Price "Data Rights" Option CLIN for the Government Purpose Rights level requested by the Government. The Government will specify a minimum of Government Purpose Rights for source code, documentation, and development artifacts consistent with DARC Site 1.

Posted: Sept. 9, 2024, 7:12 p.m. EDT
Background
The Deep Space Advanced Radar Capability (DARC) program is part of a broader initiative aimed at enhancing the United States' Space Domain Awareness (SDA) capabilities to deter aggression.

The program involves the development and installation of a pseudo-monostatic ground-based radar system, which will utilize a coherent array of steerable parabolic antennas.

The DARC system will consist of three geographically dispersed sites, approximately 120 degrees apart, to provide worldwide coverage of the geostationary orbit (GEO) belt. The Under Secretary of Defense for Acquisition and Sustainment has approved the first site as a Middle Tier Acquisition Rapid Prototype, while Sites 2 and 3 are planned for acquisition through the Major Capability Acquisition pathway.

Work Details
The contract will encompass the complete fielding of Sites 2 and 3, contractor logistics support for operations at all three sites and the Mission Operations Center (MOC), and training for site operations and maintenance personnel. Specific tasks include:
- Fielding of DARC Sites 2 and 3.
- Providing contractor logistics support for all three sites and MOC, with Site 1 support limited to two years post-operational acceptance, while Sites 2 and 3 support is limited to one year each after their respective operational acceptances.
- Training personnel for operations and maintenance across all sites.
- Production of hardware subsystems, including ordering long-lead materials for twenty-seven 15-meter dish antennas by no later than Q2 CY2024 to ensure timely delivery and installation by Q3 CY2026.
- Initiating Architecture and Engineering design processes by Q2 CY2024 to facilitate integration and testing activities starting in Q1 CY2027.

Place of Performance
The work will be performed at three geographically dispersed sites that are approximately 120 degrees apart.

Overview

Award Date
Aug. 23, 2024
Response Deadline
None
Posted
Sept. 9, 2024, 7:12 p.m. EDT (updated: Sept. 11, 2024, 5:36 p.m. EDT)
Set Aside
None
Place of Performance
Colorado Springs, CO 80914 United States
Source
SAM

Current SBA Size Standard
1350 Employees
Pricing
Fixed Price
On 9/9/24 Department of the Air Force issued Justification FA8820-24-C-B001 for Justification: Deep Space Advanced Radar Capability (DARC) Sites 2 and 3.
Primary Contact
Name
Bradley Kettlewell   Profile
Phone
None

Documents

Posted documents for Justification FA8820-24-C-B001

Question & Answer

Contract Awards

Prime contracts awarded through Justification FA8820-24-C-B001

Potential Bidders and Partners

Awardees that have won contracts similar to Justification FA8820-24-C-B001

Similar Active Opportunities

Open contract opportunities similar to Justification FA8820-24-C-B001

Additional Details

Source Agency Hierarchy
DEPT OF DEFENSE > DEPT OF THE AIR FORCE > AFSPC > SPACE AND MISSILE COMMAND > SPACE SYSTEMS2 > FA8820 SUSTAINMENT SDACP SSC/PKL
FPDS Organization Code
5700-FA8820
Source Organization Code
100149369
Last Updated
Sept. 25, 2024
Last Updated By
seneca.alvarado@spaceforce.mil
Archive Date
Sept. 25, 2024