FY24 Construction Lake Marion Orangeburg Berkeley Reach Phase 2 ?Water Line   4

ID: W912HP24R0004 • Type: Solicitation

Description

Posted: Sept. 6, 2024, 2:19 p.m. EDT
The Orangeburg-Berkely Reach Phase II Water Main contract consists of the furnishing, installing, and placing into successful operation approximately 40,703 LF of 20-inch diameter water main pipe, 2,398 LF of 26-inch diameter horizontal directionally drilled pipe, booster pump station, and all associated work. The contract includes all pipe, valves, appurtenances, roadway bores, horizontally directionally drilled pipe, backfill, compaction, testing, quality control, safety, and all other related work required to place the project into successful operation. This contract will be a portion of the Lake Marion Regional Water System with portions owned, operated, and maintained by both Santee Cooper and Berkeley County. The Contractor will be responsible for coordinating Work with local utility owners, property owners, Lake Marion Water Treatment Plant personnel, and Berkeley County. MAGNITUDE OF WORK: $10,000,000 to $25,000,000The North American Industry Classification System Code (NAICS) is: 237110 Water and Sewer Line Related . This a TOTAL SMALL BUSINESS SET-ASIDE. This Solicitation is hereby posted as of July 18, 2024. This Amendment 0001 is to clarify the type of Set-Aside and is hereby posted on 7/22/2024. The purpose of this amendment is to update the minimum requirements for Relevancy under Factor 1 - PastPerformance. See Section 00 21 16 - Instructions to Proposers for details. THIS AMENDMENT DOES NOT REOPEN COMPETITION FOR THE SUBJECT REQUIREMENT. ONLY THOSE OFFERORS WHOM SUBMITTED BY THE PREVIOUS DEADLINE ON 20 AUGUST 2024 MAY PARTICIPATE. This amendment is hereby posted on 6 September 2024.
Posted: July 22, 2024, 12:59 p.m. EDT
Posted: July 18, 2024, 2:32 p.m. EDT
Background
The Orangeburg-Berkely Reach Phase II Water Main contract consists of the furnishing, installing, and placing into successful operation approximately 40,703 LF of 20-inch diameter water main pipe, 2,398 LF of 26-inch diameter horizontal directionally drilled pipe, booster pump station, and all associated work. The contract includes all pipe, valves, appurtenances, roadway bores, horizontally directionally drilled pipe, backfill, compaction, testing, quality control, safety, and all other related work required to place the project into successful operation. This contract will be a portion of the Lake Marion Regional Water System with portions owned, operated, and maintained by both Santee Cooper and Berkeley County. The Contractor will be responsible for coordinating Work with local utility owners, property owners, Lake Marion Water Treatment Plant personnel, and Berkeley County. This Solicitation is hereby posted as of July 18, 2024.

Work Details
The work includes furnishing, installing, and placing into successful operation approximately 40,703 LF of 20-inch diameter water main pipe, 2,398 LF of 26-inch diameter horizontal directionally drilled pipe, booster pump station, and all associated work. It also involves coordinating work with local utility owners, property owners, Lake Marion Water Treatment Plant personnel, and Berkeley County. The magnitude of work is estimated to be $10 million to $25 million.

Place of Performance
The geographic location(s) for the construction projects are Orangeburg and Berkeley County.

Overview

Response Deadline
Sept. 11, 2024, 12:00 p.m. EDT (original: Aug. 20, 2024, 11:00 a.m. EDT) Past Due
Posted
July 18, 2024, 2:32 p.m. EDT (updated: Sept. 6, 2024, 2:19 p.m. EDT)
Set Aside
Small Business (SBA)
Place of Performance
Not Provided
Source
SAM

Current SBA Size Standard
$45 Million
Pricing
Likely Fixed Price
Est. Level of Competition
Average
Est. Value Range
Experimental
$10,000,000 - $25,000,000 (AI estimate)
On 7/18/24 USACE Charleston District issued Solicitation W912HP24R0004 for FY24 Construction Lake Marion Orangeburg Berkeley Reach Phase 2 ?Water Line due 9/11/24. The opportunity was issued with a Small Business (SBA) set aside with NAICS 237110 (SBA Size Standard $45 Million) and PSC Y1NE.
Primary Contact
Name
Evelyn HALLIBURTON   Profile
Phone
(843) 329-8208

Secondary Contact

Name
Addison Layfield   Profile
Phone
(843) 329-8194

Documents

Posted documents for Solicitation W912HP24R0004

Question & Answer

Opportunity Lifecycle

Procurement notices related to Solicitation W912HP24R0004

Award Notifications

Agency published notification of awards for Solicitation W912HP24R0004

Contract Awards

Prime contracts awarded through Solicitation W912HP24R0004

Incumbent or Similar Awards

Contracts Similar to Solicitation W912HP24R0004

Potential Bidders and Partners

Awardees that have won contracts similar to Solicitation W912HP24R0004

Similar Active Opportunities

Open contract opportunities similar to Solicitation W912HP24R0004

Additional Details

Source Agency Hierarchy
DEPT OF DEFENSE > DEPT OF THE ARMY > USACE > SAD > US ARMY ENGINEER DISTRICT CHARLESTO
FPDS Organization Code
2100-W912HP
Source Organization Code
500039401
Last Updated
Sept. 6, 2024
Last Updated By
EVELYN.HALLIBURTON-SHANNON@USACE.ARMY.MIL
Archive Date
Sept. 6, 2025