1. Request Engineering Service to provide RFP package DD1391, SOW, GE, SAR , NEPA, and ESS. Complete RFP Package and Put out for AWARD project FY 24 Q3 ( May 2024)
2. 35% RFP SOW/GE ( Design) submittal due date: earlier than 21 July 2023 ( FY23Q3) ; 60% Design submittal due date : earlier than 4Septemeber 2023 ( FY23 Q4); 100 % Design submittal earlier than 30 September 2023 and Final Design submittal 02 October 23
3. Request to complete a Draft DD1391 earlier than 21 May 2023 . Final DD 1391, with SME review and signed by PWO/ARE to be completed 30 October 2023.
4. Request NEPA/CATEX/ SHPO and SAR to start earlier than than 21 July 2023 and complete not later than 20 October 2023
Project Description:
The project is to replace approximately 1400 LF of existing 8 inch ACP waterline with new 8" PVC waterline
Est. Value
Min: $2,000,000
Max: $7,500,000
Max: $7,500,000
Est. Award Date
Q4 2025
Source Est. Solicitation Date
Q4 2025
Set Aside
8(a) Competitive
Pricing
Fixed-Price
Forecast Type
New
Place of Performance
TBD,
Forecast Source
Naval Facilities Engineering Command
Naval Facilities Engineering Command is forecasted to issue a new procurement for FY24: REPLACE 8 INCH ACP WATERLINE WITH 8 INCH PVC, EASEMENT IN FRONT OF BLDG 631 DRMO, NBGAH around Q4 2025 worth up to $7,500,000.
Agency
Source Level 1 Agency
Naval Facilities Engineering Command
Source Level 2 Agency
NAVFAC SYSCOM Marianas
Source Level 3 Agency
N40192
Contacts
Potential Bidders and Partners
Similar Active Opportunities
Additional Detail
Date Published
6/8/24
Date Modified
6/8/24
Additional Notes
MAC - 8A and RFP - LP